Managing complex software projects
So you have to manage a software project where products, platforms, and cross-functional teams come together. Here are the principles and practices you need to wrangle a ludicrously complex project.
Run time
60 min
Persons
1
Run time
60 min
Persons
1
What you will need
Your existing plans
Red pen
Optimism
Running the play
Use this play to...
Get off to a great start and keep the momentum high.
Increase your chances of delivering a once-in-a-career, game-changing project.
If you're struggling with shared understanding or velocity on your Health Monitor, running this play might help.
And I need this... why?
So you've been asked to lead a super complex, mission-critical technology project for your company. This is the one keeping your CEO awake at night, and probably involves one or more of the following:
integration of a platform or shared component across multiple products
collaboration across multiple teams or departments (some who haven't worked together previously)
significant technical risk
lots of dependencies between different teams
teams in multiple timezones
an aggressive timeline
intense scrutiny by senior stakeholders
Congratulations on being trusted with such a large scale, high-visibility project. You're in rare territory here – only the brave dare enter, and only the slightly crazy come out alive. This calls for a play with a twist!
Who should be involved?
As the project manager, read through this play independently and then re-tool your project plans with a focus on the stuff that really matters.
Then walk through it with your project sponsor and stakeholders (so they know you're in it to win it).
Carve out an hour and get ready to step beyond standard project management, embrace the challenge, and get ready to crush it!
Principle 1: Conscious collaboration
Plan in the same room – Every team on the project should be part of the planning process, and literally be there in the room. The travel costs are a drop in the ocean compared with the cost of building the wrong thing.
Agree on the rules of engagement up front – Answer questions like "Will platform teams do the integration work?" and "How will we engage teams like marketing, support, and operations?"
Cross-pollinate between teams – Secondments, rotations, embedded teams, or even combined teams are effective ways to reduce risk and Get $#!τ Done. The empathy and trust they build doesn't hurt, either.
Plan for roll-out, migration, and/or adoption – Don't lose sight of how you get this project to customers. Share your plans with the team and stakeholders, and keep them up to date. Bonus points for running a roll-out simulation to test and gain confidence.
Assist and reward adoption – There will be problems to flush out and fixes to make. If you're building a platform service, save some bandwidth to help the first product-side teams who adopt it.
Challenge the org chart - Bring teams from across the company together for the life of the project within a dedicated project organization.
This will help you avoid...
Wasting time trying to realign roadmaps and priorities between teams
Shoehorning in additional teams after plans are made
Unproductive meetings
Painfully protracted decision making
Doubts about whether the platform will actually work
Pro Tip: You know it's working when...
Teams trust each other
Teams' goals and roadmaps align
Engagement models and resourcing plans between teams are clearly understood
Principle 2: Shared understanding
Clarify the "why" and "what" – Set goals collectively as a team of teams so you're all aligned. Where possible, platform teams should propose initiatives in terms of business value so they can be prioritized easily against product initiatives.
Make scope and progress visible – Share your roadmap and keep it up to date. Pro-actively let your team know about changes to scope and/or timelines (there'll be plenty!).
This will help you avoid...
Teams not buying in to the project
Delayed decisions or mistakes on trade-off discussions
Insufficient resources for the scope you've agreed to
Day-to-day coordination issues like wasted work or duplicated effort
Pro Tip: You know it's working when...
Everyone on the team knows the elevator pitch by heart
Teams reference your project poster to make sure they're on course
Health Monitor sessions are trending green
Revisions to shared plans happen frequently and painlessly
Principle 3: Clear ownership
The "administrative" stuff – Assign a full-time owner for the project (if you're reading this, it's probably you!). Have your executive sponsor promote the project internally, and be on call to unblock when bottlenecks pop up.
The technical stuff – Include a cross-product architect in your project team so they can look after high-level design and implementation concerns. Agree on who owns the overall customer experience (e.g., platform, or product?), as well as who owns each major deliverable.
Map it out – Run the Roles and Responsibilities play with the entire project team (or representatives from each sub-team). Bonus points for running it within each sub-team, too.
This will help you avoid...
Team members treading on each other's toes
Generally creating bottlenecks
Work falling through the cracks
Bloodthirsty sponsors who didn't get an update about changes to scope or timing
Pro Tip: You know it's working when...
Decisions are made quickly
Stakeholders know who to contact with questions
The full-time owner communicates updates each week
Deliverables are shipped on time
Principle 4: Trust
Recruit in the right people – Gather your best communicators, integrators, those that quickly build trust & have a positive attitude. You need folks with a high degree of attention to detail and urgency.
Swap trade secrets – Encourage the platform teams to draw on the product teams' wealth of knowledge about your customers. And bring the product teams up to speed on platform work through brown-bag presos, internal blogs, lunch dates, etc.
Build momentum – Go for a shared quick win early on to boost morale and cement the teams' trust in each other. And don't forget to run Health Monitor sessions every month!
This will help you avoid...
Frequent roadblocks and broken promises
Uninspired problem-solving
Low morale
Pro Tip: You know it's working when...
Teams enjoy working with each other
Milestones are celebrated and communicated jointly
Interpersonal or collaboration issues are discussed openly and resolved quickly
Principle 5: Shared milestones
Track your progress – Share your project timeline and use it as your single source of truth. Keep it updated to reflect reality, even if this means weekly adjustments. Which it will.
Ship (and celebrate) in small increments – Recruit members of the project team to act as cheerleaders who help keep velocity and morale high.
Collectively own quality – Build integration and testing time into the plan, and make sure your "definition of done" is agreed upon and documented.
This will help you avoid...
Surprises during testing
Slow (or no) progress
Misaligned deliverables and delivery dates
Pro Tip: You know it's working when...
Stakeholders are delighted by your steady progress
Customers start reaping the benefits well before the project is complete
You're getting value out of the platform faster than expected, and with little overhead
Principle 6: Effective decisions
Be thoughtful – Take both long and short-term implications into account. Carefully consider who should make the call. Don't just assume the full-time owner or exec sponsor is best suited.
Optimize for efficiency – Run the Trade-off Sliders play so individuals and teams are empowered to make every-day decisions autonomously. For major decisions, use the DACI framework.
Organize and communicate – Set up a decision register to keep track of what's being (or has been) decided, and refer to it in your weekly project communications.
This will help you avoid...
Teams becoming more uncertain with every decision they make as there's too much information lying "below the waterline"
Considering a solution or timeframe based on outdated or incorrect information
You revise and recount the same decision numerous times
Pro Tip: You know it's working when...
Decisions are made quickly
Different views are heard before accepting a single decision
Decisions aren't being reopened or disputed
Principle 7: Manage dependencies
Anticipate bottlenecks – Make a table or diagram that maps out who your team relies on, and who relies on your team.
Keep tabs on it – Assign one owner from each side who looks after each dependency. Make sure the dependency owners understand and communicate the impact of changes to all upstream and downstream teams.
This will help you avoid...
Downstream delays and missed milestones
Frustration, flailing, and general hand-wringing
Pro Tip: You know it's working when...
You have a concise, comprehensive, self-serve way to keep track of dependencies
You can visualize the dependencies as a map or chart
Principle 8: Communicate, adapt, celebrate!
Create a shared communication plan – Weekly: face-to-face meeting for general project updates. Fortnightly: demos, status updates to stakeholders. Monthly: Health Monitors, project "all-hands". Or something like that. Enlist your engineering managers, PMs, and architects to help get comms out.
Make the most of project meetings – Include a 10-minute demo or problem-solving session in your weekly meetings to keep the room engaged.
Sync 1-on-1 – Meet weekly or biweekly with the team lead and product manager of each work stream to check progress against your schedule, identify any schedule changes, discuss new risks or issues, and talk about team morale.
Be easy to find – Establish a HipChat room or Confluence page as your forum for Q&A and/or escalating problems.
Celebrate even the small wins – They snowball into big wins faster than you'd think!
This will help you avoid...
Team members losing sight of the bigger picture
Low morale and high burnout
Unfocused, unproductive meetings
Stakeholders feeling blind-sided by changes to status, risks, milestone dates, etc.
Pro Tip: You know it's working when...
Stakeholders look forward to receiving your status updates
Team members are aware of the big picture
Momentum builds up and becomes unstoppable
Follow-ups
You've probably recognized some gaps in your project plans, and have ideas on how you'll change your approach.
The kicker here, though, is to not add more work!
Kill activities or cancel meetings that aren't adding value and re-purpose that time for the activites you've picked up.
Carve out an hour and get ready to step beyond standard project management, embrace the challenge, and get ready to crush it!
Principle 1: Conscious collaboration
Plan in the same room – Every team on the project should be part of the planning process, and literally be there in the room. The travel costs are a drop in the ocean compared with the cost of building the wrong thing.
Agree on the rules of engagement up front – Answer questions like "Will platform teams do the integration work?" and "How will we engage teams like marketing, support, and operations?"
Cross-pollinate between teams – Secondments, rotations, embedded teams, or even combined teams are effective ways to reduce risk and Get $#!τ Done. The empathy and trust they build doesn't hurt, either.
Plan for roll-out, migration, and/or adoption – Don't lose sight of how you get this project to customers. Share your plans with the team and stakeholders, and keep them up to date. Bonus points for running a roll-out simulation to test and gain confidence.
Assist and reward adoption – There will be problems to flush out and fixes to make. If you're building a platform service, save some bandwidth to help the first product-side teams who adopt it.
Challenge the org chart - Bring teams from across the company together for the life of the project within a dedicated project organization.
This will help you avoid...
Wasting time trying to realign roadmaps and priorities between teams
Shoehorning in additional teams after plans are made
Unproductive meetings
Painfully protracted decision making
Doubts about whether the platform will actually work
Pro Tip: You know it's working when...
Teams trust each other
Teams' goals and roadmaps align
Engagement models and resourcing plans between teams are clearly understood
Principle 2: Shared understanding
Clarify the "why" and "what" – Set goals collectively as a team of teams so you're all aligned. Where possible, platform teams should propose initiatives in terms of business value so they can be prioritized easily against product initiatives.
Make scope and progress visible – Share your roadmap and keep it up to date. Pro-actively let your team know about changes to scope and/or timelines (there'll be plenty!).
This will help you avoid...
Teams not buying in to the project
Delayed decisions or mistakes on trade-off discussions
Insufficient resources for the scope you've agreed to
Day-to-day coordination issues like wasted work or duplicated effort
Pro Tip: You know it's working when...
Everyone on the team knows the elevator pitch by heart
Teams reference your project poster to make sure they're on course
Health Monitor sessions are trending green
Revisions to shared plans happen frequently and painlessly
Principle 3: Clear ownership
The "administrative" stuff – Assign a full-time owner for the project (if you're reading this, it's probably you!). Have your executive sponsor promote the project internally, and be on call to unblock when bottlenecks pop up.
The technical stuff – Include a cross-product architect in your project team so they can look after high-level design and implementation concerns. Agree on who owns the overall customer experience (e.g., platform, or product?), as well as who owns each major deliverable.
Map it out – Run the Roles and Responsibilities play with the entire project team (or representatives from each sub-team). Bonus points for running it within each sub-team, too.
This will help you avoid...
Team members treading on each other's toes
Generally creating bottlenecks
Work falling through the cracks
Bloodthirsty sponsors who didn't get an update about changes to scope or timing
Pro Tip: You know it's working when...
Decisions are made quickly
Stakeholders know who to contact with questions
The full-time owner communicates updates each week
Deliverables are shipped on time
Principle 4: Trust
Recruit in the right people – Gather your best communicators, integrators, those that quickly build trust & have a positive attitude. You need folks with a high degree of attention to detail and urgency.
Swap trade secrets – Encourage the platform teams to draw on the product teams' wealth of knowledge about your customers. And bring the product teams up to speed on platform work through brown-bag presos, internal blogs, lunch dates, etc.
Build momentum – Go for a shared quick win early on to boost morale and cement the teams' trust in each other. And don't forget to run Health Monitor sessions every month!
This will help you avoid...
Frequent roadblocks and broken promises
Uninspired problem-solving
Low morale
Pro Tip: You know it's working when...
Teams enjoy working with each other
Milestones are celebrated and communicated jointly
Interpersonal or collaboration issues are discussed openly and resolved quickly
Principle 5: Shared milestones
Track your progress – Share your project timeline and use it as your single source of truth. Keep it updated to reflect reality, even if this means weekly adjustments. Which it will.
Ship (and celebrate) in small increments – Recruit members of the project team to act as cheerleaders who help keep velocity and morale high.
Collectively own quality – Build integration and testing time into the plan, and make sure your "definition of done" is agreed upon and documented.
This will help you avoid...
Surprises during testing
Slow (or no) progress
Misaligned deliverables and delivery dates
Pro Tip: You know it's working when...
Stakeholders are delighted by your steady progress
Customers start reaping the benefits well before the project is complete
You're getting value out of the platform faster than expected, and with little overhead
Principle 6: Effective decisions
Be thoughtful – Take both long and short-term implications into account. Carefully consider who should make the call. Don't just assume the full-time owner or exec sponsor is best suited.
Optimize for efficiency – Run the Trade-off Sliders play so individuals and teams are empowered to make every-day decisions autonomously. For major decisions, use the DACI framework.
Organize and communicate – Set up a decision register to keep track of what's being (or has been) decided, and refer to it in your weekly project communications.
This will help you avoid...
Teams becoming more uncertain with every decision they make as there's too much information lying "below the waterline"
Considering a solution or timeframe based on outdated or incorrect information
You revise and recount the same decision numerous times
Pro Tip: You know it's working when...
Decisions are made quickly
Different views are heard before accepting a single decision
Decisions aren't being reopened or disputed
Principle 7: Manage dependencies
Anticipate bottlenecks – Make a table or diagram that maps out who your team relies on, and who relies on your team.
Keep tabs on it – Assign one owner from each side who looks after each dependency. Make sure the dependency owners understand and communicate the impact of changes to all upstream and downstream teams.
This will help you avoid...
Downstream delays and missed milestones
Frustration, flailing, and general hand-wringing
Pro Tip: You know it's working when...
You have a concise, comprehensive, self-serve way to keep track of dependencies
You can visualize the dependencies as a map or chart
Principle 8: Communicate, adapt, celebrate!
Create a shared communication plan – Weekly: face-to-face meeting for general project updates. Fortnightly: demos, status updates to stakeholders. Monthly: Health Monitors, project "all-hands". Or something like that. Enlist your engineering managers, PMs, and architects to help get comms out.
Make the most of project meetings – Include a 10-minute demo or problem-solving session in your weekly meetings to keep the room engaged.
Sync 1-on-1 – Meet weekly or biweekly with the team lead and product manager of each work stream to check progress against your schedule, identify any schedule changes, discuss new risks or issues, and talk about team morale.
Be easy to find – Establish a HipChat room or Confluence page as your forum for Q&A and/or escalating problems.
Celebrate even the small wins – They snowball into big wins faster than you'd think!
This will help you avoid...
Team members losing sight of the bigger picture
Low morale and high burnout
Unfocused, unproductive meetings
Stakeholders feeling blind-sided by changes to status, risks, milestone dates, etc.
Pro Tip: You know it's working when...
Stakeholders look forward to receiving your status updates
Team members are aware of the big picture
Momentum builds up and becomes unstoppable
Follow-ups
You've probably recognized some gaps in your project plans, and have ideas on how you'll change your approach.
The kicker here, though, is to not add more work!
Kill activities or cancel meetings that aren't adding value and re-purpose that time for the activites you've picked up.
Variations
Share the stakeholder list widely so everyone knows who's who.
Resist the temptation to reconcile existing independent plans - it's much better to start from scratch and build an integrated plan that involves all the teams.
In addition to planning together up front, remember to re-plan together continuously throughout the project.
Don't feel confined by the org chart – challenge it, and bring teams together.
Limit the number of cross-product projects that each team is working on.
Make sure all teams are specifically including time in their schedules for non-project time (e.g. conferences, leave, company events, other meetings, etc).

Still have questions?
Start a conversation with other Atlassian Team Playbook users, get support, or provide feedback.
Plays you may like

Goal-setting
Goals, Signals, and Measures
Make sure your team is focused and know what success looks like.

Project planning
Mindmapping
Explore a problem space and organize your ideas for solutions.