Jira Versions Tutorial

In this tutorial, we'll explain how to work with versions in Jira.

TIME

10 minute read. Complete over 2 weeks or more.

AUDIENCE

  • You're familiar with how Scrum and/or Kanban work in Jira

  • You have the Administer Spaces permission for all spaces on your Scrum or Kanban board. See Managing space permissions for more info.

PREREQUISITE

  • You've created a Jira account

  • You've created a Jira Scrum or Kanban space

  • You've filled your space with work items

  • You’ve enabled the Releases feature under your space settings

What is a version in Jira?

In Jira, versions represent points-in-time for a space. They help you organize your work by giving you milestones to aim for. You can assign work items in your space to a specific version, and organize your sprints around completing work in that version.

Step 1: Create a version in Jira

  1. Navigate to your space.

  2. In the space menu, click on Releases.

  3. Click on Create version.

  4. Select the Name text box and enter a name. Optionally, schedule a Start date and/or Release date, or add a Description of this version. Click Save. Version names are typically numeric, for example, 1.0 or 2.1.1. You could also consider using an internal codename.

How many versions should I create?

You can create as many as you think is necessary. For example, you might create several versions, to plan ahead. Or you might just have one or two versions for now.

Once you create a version, the Affects version and Fix version fields will become available on your work items. 

Affects version is the version in which a bug or problem was found. Although it can be useful for tracking problems, it isn't used very often in Jira.

Fix version is the version where you plan on releasing a feature or bugfix to customers. This field is used for release planning, monitoring progress and velocity, and is used widely in reporting. This is most likely the field you want.

Step 2: Add work items to version

If your space has a backlog

  1. Navigate to the space Backlog.

  2. Open the Versions panel on the left.

  3. Drag a work item to the version you want to add it to.

If your space doesn't have a backlog

  • Open the work item you want to add to a version.

  • Find the Fix version/s field, and enter the version you want to add the work item to.

Step 3: Monitoring the progress of a version

Jira gives you many tools you can use to check the progress of a version. We'll discuss a few of them here.

Timeline

The timeline view in Jira brings your work items and releases into a single place where you can plan deliverables, track progress, and share updates with stakeholders. Once you’ve configured your timeline to show Releases, you will be able to see scheduled releases along the timeline and access important details about each release directly in the timeline view.

To show releases on your timeline:

  1. Click View settings on the top right corner of your timeline

  2. Check the box next to Releases

To plan and track releases on your timeline:

  • When planning future releases or tracking a release in progress, you can quickly determine the status of each release based on the release icon:

    a. A blue circle indicates the release is UNRELEASED and has not passed its release date b. A red circle with an exclamation point indicates the release is UNRELEASED and overdue c. A green circle with a checkmark indicates the release has been RELEASED

  • Use the Versions filter to display only the work items related to the selected release(s) on the timeline. This allows you to see all the work items related to a specific deliverable scheduled over time.

  • Click on any release icon to view important details such as progress, dates, and description. Optionally, check the box next to Highlight on timeline to visualize the release date on your timeline. This allows you to see how a specific deliverable is tracking towards its release date.

    • 1. Release status: this appears as UNRELEASED, RELEASED, or ARCHIVED.

    • 2. Release description: this describes the deliverables in your release and can be added upon release creation or edited in the Releases tab.

    • 3. Release progress bar: this reflects the statuses of work items assigned to the release and will automatically update as work item statuses change.

    • 4. Start date and release dates: the start and release dates scheduled for your release which can be edited in the Releases tab.

    • 5. Option to highlight release date on the timeline (shown as vertical blue line)

The release hub

The release hub provides a place for you to manage all your releases. It also gives you information on the status of your releases, and a breakdown of the number of work items in each version.

To navigate to the release hub:

  1. Go to your space.

  2. In the space menu, select Releases.

  • 1. Quick filters: Focus on specific versions by filtering out the ones you aren't interested in.

  • 2. Version list: Drag and drop versions to reorder them.

  • 3. Status: Versions can have one of three statuses: UNRELEASED, RELEASED, or ARCHIVED.

  • 4. Progress: This shows how many work items have been assigned to the version, and how many are in each status.

Want more information to help you monitor your releases?

If you integrate Jira with your Bitbucket repository, you'll also see development information here relating to your commits, branches, and pull requests.

Release Burndown report (Scrum only)

The release burndown report shows how much work has been completed, and the total work remaining. Burndown charts are used to predict your team's likelihood of completing their work in the time available. They're also great for keeping the team aware of any scope creep that occurs.

Note that to use the release burndown chart, you'll need to estimate your work items. For more information, check out our guide on burndown charts.

To view the release burndown report:

  • Navigate to your space.

  • In the space menu, select Reports.

  • Select the Release Burndown.

  • Release menu: Select which release to view data for.

  • Work added: The dark blue segment shows the amount of work added to the release in each sprint. In this example, work is measured in story points.

  • Work remaining: The light blue segment shows the amount of work remaining in the release.

  • Work completed: The green segment represents how much work is completed for the release in each sprint.

  • Projected completion: The report projects how many sprints it will take to complete the release, based on the team's velocity.

For more in-depth information, check out our release burndown chart documentation.

Step 4: Complete a version

It's time to turn your team's hard work into a software release. By this stage, you should be confident that your version is ready to be released – work items are complete, code is checked in, reviewed, and merged, builds are passing, etc.

To deploy a release, you would typically release the version in Jira, build the release, then deploy the release to the required environment. 

To complete a version

  1. Navigate to your space.

  2. In the space menu, select Releases.

  3. For the version you want to release, select Actions (•••) > Release.

On Kanban boards, you can also release all work items in the Done column as a new version directly from the board itself.

Versions and Jira automation

You can use automation to supercharge how you use versions in Jira. See this automation rule and 100s more in the Jira Automation Template Library. Go to library

What to learn more?

For more detailed information on working with versions in Jira, check out our versions documentation.

Have questions? Ask the Atlassian Community.

Browse topics

Learn how to use versions in Jira

The guide to using versions in Jira

Get started for free with Jira

Jira Versions Tutorial

In this tutorial, we'll explain how to work with versions in Jira.

TIME

10 minute read. Complete over 2 weeks or more.

AUDIENCE

  • You're familiar with how Scrum and/or Kanban work in Jira

  • You have the Administer Spaces permission for all spaces on your Scrum or Kanban board. See Managing space permissions for more info.

PREREQUISITE

  • You've created a Jira account

  • You've created a Jira Scrum or Kanban space

  • You've filled your space with work items

  • You’ve enabled the Releases feature under your space settings

What is a version in Jira?

In Jira, versions represent points-in-time for a space. They help you organize your work by giving you milestones to aim for. You can assign work items in your space to a specific version, and organize your sprints around completing work in that version.

Step 1: Create a version in Jira

  1. Navigate to your space.

  2. In the space menu, click on Releases.

  3. Click on Create version.

  4. Select the Name text box and enter a name. Optionally, schedule a Start date and/or Release date, or add a Description of this version. Click Save. Version names are typically numeric, for example, 1.0 or 2.1.1. You could also consider using an internal codename.

How many versions should I create?

You can create as many as you think is necessary. For example, you might create several versions, to plan ahead. Or you might just have one or two versions for now.

Once you create a version, the Affects version and Fix version fields will become available on your work items. 

Affects version is the version in which a bug or problem was found. Although it can be useful for tracking problems, it isn't used very often in Jira.

Fix version is the version where you plan on releasing a feature or bugfix to customers. This field is used for release planning, monitoring progress and velocity, and is used widely in reporting. This is most likely the field you want.

Step 2: Add work items to version

If your space has a backlog

  1. Navigate to the space Backlog.

  2. Open the Versions panel on the left.

  3. Drag a work item to the version you want to add it to.

If your space doesn't have a backlog

  • Open the work item you want to add to a version.

  • Find the Fix version/s field, and enter the version you want to add the work item to.

Step 3: Monitoring the progress of a version

Jira gives you many tools you can use to check the progress of a version. We'll discuss a few of them here.

Timeline

The timeline view in Jira brings your work items and releases into a single place where you can plan deliverables, track progress, and share updates with stakeholders. Once you’ve configured your timeline to show Releases, you will be able to see scheduled releases along the timeline and access important details about each release directly in the timeline view.

To show releases on your timeline:

  1. Click View settings on the top right corner of your timeline

  2. Check the box next to Releases

To plan and track releases on your timeline:

  • When planning future releases or tracking a release in progress, you can quickly determine the status of each release based on the release icon:

    a. A blue circle indicates the release is UNRELEASED and has not passed its release date b. A red circle with an exclamation point indicates the release is UNRELEASED and overdue c. A green circle with a checkmark indicates the release has been RELEASED

  • Use the Versions filter to display only the work items related to the selected release(s) on the timeline. This allows you to see all the work items related to a specific deliverable scheduled over time.

  • Click on any release icon to view important details such as progress, dates, and description. Optionally, check the box next to Highlight on timeline to visualize the release date on your timeline. This allows you to see how a specific deliverable is tracking towards its release date.

    • 1. Release status: this appears as UNRELEASED, RELEASED, or ARCHIVED.

    • 2. Release description: this describes the deliverables in your release and can be added upon release creation or edited in the Releases tab.

    • 3. Release progress bar: this reflects the statuses of work items assigned to the release and will automatically update as work item statuses change.

    • 4. Start date and release dates: the start and release dates scheduled for your release which can be edited in the Releases tab.

    • 5. Option to highlight release date on the timeline (shown as vertical blue line)

The release hub

The release hub provides a place for you to manage all your releases. It also gives you information on the status of your releases, and a breakdown of the number of work items in each version.

To navigate to the release hub:

  1. Go to your space.

  2. In the space menu, select Releases.

  • 1. Quick filters: Focus on specific versions by filtering out the ones you aren't interested in.

  • 2. Version list: Drag and drop versions to reorder them.

  • 3. Status: Versions can have one of three statuses: UNRELEASED, RELEASED, or ARCHIVED.

  • 4. Progress: This shows how many work items have been assigned to the version, and how many are in each status.

Want more information to help you monitor your releases?

If you integrate Jira with your Bitbucket repository, you'll also see development information here relating to your commits, branches, and pull requests.

Release Burndown report (Scrum only)

The release burndown report shows how much work has been completed, and the total work remaining. Burndown charts are used to predict your team's likelihood of completing their work in the time available. They're also great for keeping the team aware of any scope creep that occurs.

Note that to use the release burndown chart, you'll need to estimate your work items. For more information, check out our guide on burndown charts.

To view the release burndown report:

  • Navigate to your space.

  • In the space menu, select Reports.

  • Select the Release Burndown.

  • Release menu: Select which release to view data for.

  • Work added: The dark blue segment shows the amount of work added to the release in each sprint. In this example, work is measured in story points.

  • Work remaining: The light blue segment shows the amount of work remaining in the release.

  • Work completed: The green segment represents how much work is completed for the release in each sprint.

  • Projected completion: The report projects how many sprints it will take to complete the release, based on the team's velocity.

For more in-depth information, check out our release burndown chart documentation.

Step 4: Complete a version

It's time to turn your team's hard work into a software release. By this stage, you should be confident that your version is ready to be released – work items are complete, code is checked in, reviewed, and merged, builds are passing, etc.

To deploy a release, you would typically release the version in Jira, build the release, then deploy the release to the required environment. 

To complete a version

  1. Navigate to your space.

  2. In the space menu, select Releases.

  3. For the version you want to release, select Actions (•••) > Release.

On Kanban boards, you can also release all work items in the Done column as a new version directly from the board itself.

Versions and Jira automation

You can use automation to supercharge how you use versions in Jira. See this automation rule and 100s more in the Jira Automation Template Library. Go to library

What to learn more?

For more detailed information on working with versions in Jira, check out our versions documentation.

Have questions? Ask the Atlassian Community.

Recommended for you

Templates

Ready-made Jira templates

Browse our library of custom Jira templates for various teams, departments, and workflows.

Product guide

A comprehensive introduction to Jira

Use this step-by-step guide to discover essential features and the best practices to maximize your productivity.